Explosives information bulletin no. 37 | 01 July 2023 | Version 31
This bulletin lists the fees (in dollar amounts) for a licence (authority), security clearance, trial or authorisation of an explosive as prescribed in section 14 of the Explosives Act 1999 and schedule 2 of the Explosives Regulation 2017 (as fee units).
For the 2023-24 financial year, the fee unit amount was increased by 3.4% and takes effect on 1 July 2023.
Licence class | Licence type | Licence fee and period of licence | |
---|---|---|---|
1 year | 5 years | ||
Licence to import/export explosives | (a) for blasting explosives | $804.54 | $4,022.70 |
(b) for propellant powders and ammunition | $534.24 | $2,671.20 | |
(c) for fireworks | $393.58 | $1,967.90 | |
(d) for distress signals | $120.31 | $601.55 | |
(e) for an explosive not mentioned in items (a) to (d) including SSAN | $393.58 | $1,967.90 | |
Licence to manufacture explosives | (a) for an explosives factory other than a mobile manufacturing unit | $498.41 | $2,492.05 |
(b) for a mobile manufacturing unit | $229.28 | $1,146.40 | |
(c) for manufacture explosives at a place of use that is not an explosives factory | $115.54 | $577.70 | |
Licence to sell explosives | (a) for blasting explosives | $97.26 | $486.30 |
(b) for propellant powders | $97.26 | $486.30 | |
(c) for fireworks | $97.26 | $486.30 | |
(d) for ammunition | $17.97 | $89.85 | |
(e) for an explosive not mentioned in items (a) to (d) including SSAN | $97.26 | $486.30 | |
Licence to store explosives | (a) for blasting explosives up to 100 kg | $127.52 | $637.60 |
(b) for blasting explosives greater than 100 kg | $498.41 | $2,492.05 | |
(c) for propellant powders up to 100 kg | $47.91 | $239.55 | |
(d) for propellant powders greater than 100 kg but not greater than 250 kg | $127.52 | $637.60 | |
(e) for propellant powders greater than 250 kg | $498.41 | $2,492.05 | |
(f) for fireworks up to 100 kg (gross weight) | $47.91 | $239.55 | |
(g) for fireworks greater than 100 kg (gross weight) | $498.41 | $2,492.05 | |
(h) for explosives not mentioned in items (a) to (g) not more than 100 kg including SSAN | $47.91 | $239.55 | |
(j) for explosives not mentioned in items (a) to (g) greater than 100 kg including SSAN | $498.41 | $2,492.05 |
Licence class | Licence fee and period of licence | ||
---|---|---|---|
1 Year | 3 Years | 5 Years | |
Licence to transport explosives (per vehicle) | $127.52 | N/A | $637.60 |
Explosives driver licence | $68.95 | N/A | $344.75 |
Licence to use explosives | $68.95 | N/A | $344.75 |
Shotfirer licence | $68.95 | N/A | $344.75 |
Fireworks contractor licence | $458.24 | $1,374.72 | N/A |
Fireworks operator licence | $146.28 | $438.84 | N/A |
Licence to collect ammunition | $17.97 | N/A | $89.85 |
Application type | Regulatory fee |
---|---|
Permit to import explosives | Nil |
Permit to export explosives | Nil |
Permit to store explosives | Nil |
Application for explosives trial approval | Nil |
Request for explosive to be declared an authorised explosive | $164.94 |
Transfer of licence | $50.14 |
Replacement of licence or security clearance | $50.14 |
Application for approval of a design of a tank under s. 114 | $304.60 |
Note: Security clearance fees are non-refundable. Security clearance fees are only payable when completing a security clearance application at an Australia Post outlet.
Type of security check | Fee |
---|---|
Security clearance – new application | 5 years: $215.60 |
Security clearance - renewal | 5 years: $172.46 |
Number of explosives workers | Fee |
---|---|
if the number of explosives workers working under the authority during the quarter is 5 or fewer | Nil |
if the number of explosives workers working under the authority during the quarter is more than 5 but not more than 10—for each explosives worker working under the authority during the quarter | $33.92 |
if the number of explosives workers working under the authority during the quarter is more than 10 but not more than 19—for each explosives worker working under the authority during the quarter | $135.68 |
if the number of explosives workers working under the authority during the quarter is more than 19 but not more than 99—for each explosives worker working under the authority during the quarter | $254.14 |
if the number of explosives workers working under the authority during the quarter is more than 99—for each explosives worker working under the authority during the quarter | $338.94 |
Number of explosives workers | Fee |
---|---|
if the number of explosives workers working under the authority during the quarter is 5 or fewer | Nil |
if the number of explosives workers working under the authority during the quarter is more than 5 but not more than 10—for each explosives worker working under the authority during the quarter | $135.68 |
if the number of explosives workers working under the authority during the quarter is more than 10 but not more than 19—for each explosives worker working under the authority during the quarter | $542.72 |
if the number of explosives workers working under the authority during the quarter is more than 19 but not more than 99—for each explosives worker working under the authority during the quarter | $1016.54 |
if the number of explosives workers working under the authority during the quarter is more than 99—for each explosives worker working under the authority during the quarter | $1355.74 |
Fee type | Fee |
---|---|
Fee for late safety and health census (s 181(3)) | $128.68 |
*The completed application form for a licence, permit, and/or authorisation, and all required items must be lodged with the Explosives Inspectorate prior to a BPOINT payment link being provided to the applicant
Fees paid by an applicant for an authority (licence, permit or authorisation) may be refunded if:
Contact: explosives@rshq.qld.gov.au
Issued by Resources Safety & Health Queensland
Find more safety notices
Search the hazards database
All information on this page (Regulatory and security clearance fees (2023-24) - https://www.rshq.qld.gov.au/safety-notices/explosives/regulatory-and-security-clearance-fees) is correct as of time of printing (Apr 26, 2024 7:38 pm).